3-Point Risk Impacts

As a risk user, you may want to set the minimum, maximum, and most likely impacts to time and cost.

When you select the Triangle in the Type column on the S3 // Risk tab Activities grid, Acumen calculates the minimum, most likely, and maximum impacts to time and cost.

The Activity Details Risk Events tab includes the Type, Most Likely Duration, and Most Likely Cost columns. Acumen enables the Most Likely Duration/Cost columns when you set Type to Triangle.

The Risk Register Events tab includes the Most Likely Duration and Most Likely Costs columns. Acumen enables these when you set Type to Triangle.